Roofing Pt2

This week’s weather has been kind enough to allow us install woodfibre boards on top of roof I-beams, and wrap the boards with windtightness membrane, held down by timber counterbattens. Larger timber battens will provide support for the corrugated metal roof. It’s good to have two layers of protection above the straw panels.

We have been tweaking the design of junctions between timber cladding and roof with Mike, and decided that it’s best to finish off installation of external woodfibre boards to walls and insect mesh to close off vented cavities before the corrugated roof goes on.

On Saturday Joyce & me finished off sealing the last charred cedar cladding boards, which was very satisfying to see. It’s now all stacked and ready to use.

There was a bit of excitement when a herd of escapee cows passed our site – I wonder if they wanted to have a peek at this straw filled passivhaus? 😉